The Parrish McCall James W. “Bill” Heavener Football Training Center project team has been working diligently to bring you this new state-of-the-art facility at the University of Florida. 🐊🏈
In recent weeks, the team has been working heavily on site work and utilities, including the following site activities:
-Over-excavation to remove unsuitable soils from the building footprint
-Demolition and construction of the retaining wall to reshape the site footprint
-Offsite work to bring utilities to the new facility, including steam and condensate, chilled water, electrical, reclaimed water, domestic water and storm water
-Reshaping the south side (main entrance) to the new facility, including removal of existing utilities and installation of new utilities
-Excavation of facility’s hydrotherapy pit
We are excited and honored to work alongside the University of Florida and the Florida Gators to bring you this new facility and look forward to sharing more updates in the coming weeks.
To stay up to date on the progress of this project, please visit the Florida Gators Football official project site at gatorgamechanger.com.